Chinese New Year 2027: When to Place Knitwear Orders

Short answer: Chinese New Year 2027 falls on Saturday 6 February, and the practical shutdown for knitwear runs from mid-January to late March — not the two weeks the official holiday suggests. To ship before the holiday, your order must be confirmed by early November and finished by mid-December. To produce after it, plan for full capacity in late March, not late February.
Every year in February the same emails arrive: the factory is not answering, the vessel is full, and the pre-production sample approved on 28 December has not moved. Chinese New Year is the most predictable disruption in apparel sourcing, and it is still the one that catches the most buyers out.
Why Knitwear Loses More Weeks Than Cut and Sew
The 2027 Calendar That Actually Matters
The Two Mistakes That Actually Cost Money
Plan for Post-Holiday Quality Drift
The expensive part of Chinese New Year is not the delay; it is the batch you receive in March and do not inspect. Put a pre-shipment inspection on the first lot produced after the restart, and do not send that first lot to a new retail account. If one style cannot be late, split it: ship 60% before the holiday and 40% after, so a March problem does not empty the shelf.
What to Do With the Dead Weeks
Conclusion
Chinese New Year is not a risk you manage; it is a calendar you plan around. The buyers who get through it are not the ones who find a factory that stays open — those factories are usually the ones you should not want. They are the ones who decided in October what had to ship in December, and accepted that everything else is a March conversation.
Key Takeaways for Buyers
How We Plan Around the Holiday
We send clients a shutdown and restart schedule with dates rather than adjectives, and we stop accepting new styles for pre-holiday production at a date we publish in advance instead of quietly letting a January order slide into March. Where a programme genuinely cannot make it, we say so in November while there is still a freight option — air freighting 300 kg of sweaters is expensive, but it is cheaper than missing a launch. Ask us for the 2027 calendar and we will send it with our mill-specific dates attached.
Related Products
Related Articles
- How Long Does Knitwear Manufacturing Take? A Lead Time Guidelead-time · production

- Why Apparel Orders Get Delayed (and How to Prevent It)lead-time · production

- How Long Does Custom Knitwear Production Take?lead-time · sourcing

- Knitwear Tech Packs: The Sections Factories Actually Readtech-pack · guide

- Sampling: Why Your PP Sample Is the One That Matterssampling · production

- Switching Suppliers: Run Both for One Ordersupplier · sourcing

Comments (0)
Be the first to leave a comment!